|
1.1 Basis 
The main goal of today's waste management is an
optimised ecological and economical handling of the waste. It is based on
the following strategy:
-
the production of waste has to be reduced at its
source;
-
the use of dangerous materials and substances is
reduced to the minimum;
-
waste is recycled if ever possible;
-
for the left over of the waste an ecological way is
chosen for a definite disposal.
This description gives in a concise form the conceptual
design, the technology and the construction part for the waste treatment
plant. Furthermore, information concerning the environmental impact are
given under a forthcoming section.
A thermal waste treatment plant based on stoker type
grate incineration is according to our experience the most reliable and
economical solution. An additional advantage is the production of
electricity with good efficiency. A semi-dry flue gas treatment provides
the benefit of simple and robust technology combined with little residues
to deposit.
1.2 Process technology part 
1.2.1 Delivery and storage
of the waste 
The waste will be delivered by road transport and off
loaded into the waste pit. The waste pit is sized for a capacity of at
least five days in order to guarantee a continuous treatment of the waste
even in case of heavy fluctuations in delivery. The incinerator will be
fed by specially designed waste crane.
1.2.2 Incinerator and boiler 
The incineration of the waste takes place on a stoker
type grate. The slag produced during this treatment will be removed
through a slag quench tank and extractor located underneath the grate. The
boiler located above the grate produces live steam by cooling the flue gas
from initially minimum of 850°C down to about 230°C at boiler outlet. To
guarantee an efficient burnout and the minimum temperature of the flue gas
in the post combustion zone at 850°C, this during the start-up phase and
temperature fluctuations at normal operation, start up and/or support
burners are installed.
The combustion air will be partially drawn from the
waste pit, preheated and injected through the grate and the waste layer
into the combustion chamber (primary air). Additional air will be drawn
above the slag extractor and injected into the combustion chamber above
the grate (secondary air), in order to achieve a complete post-combustion
of the flue gas. The membrane walls of the boiler around the combustion
chamber are protected by refractory lining against corrosive effects of
the flame and hot flue gas.
Nitrogen oxides (NOx) formed during the
combustion will be reduced using ammonia (NH3) injection into
the post-combustion chamber by a so called selective non-catalytic
reduction (SNCR) process. The fly ash contained in the flue gas falls into
the ash hoppers of the boiler and will be transported by a pneumatic or
mechanic transport system into the ash silo.
1.2.3 Energy utilisation 
The steam produced in the boiler flows to a condensing
turbine which is used for electric power generation. The turbine has steam
extraction's at the appropriate pressure stages to cover the internal
needs of steam (air preheaters, feed-water turbo pump, feed-water
preheater, deaerator etc.).
The electric power generator supplies electricity to
all plant internal installations. The surplus production is fed into the
public electricity network. In case of a turbine failure as well as during
the start-up and shut-down phases, the steam flows through the turbine
by-pass directly to the air cooled condenser (ACC).
1.2.4 Flue gas cleaning 
A semi-dry flue gas cleaning is proposed before the
gases are released into the atmosphere. The flue gas cleaning, according
to the state of the art, includes the following components:
1.2.5 Treatment of residues 
The slag falls from the grate into the slag quench
tank. The quenched slag will be conveyed to a special slag bunker
underneath the boiler. By means of a magnetic drum the iron can be
separated from the slag which then can be treated externally for further
use in road construction.
Optionally, the boiler ash can be washed with process
water. After drying on a belt filter, the ash can be used together with
the slag. So the extracted hazardous metals would be chemically fixed to
the hydrated lime used in the semi-dry reactor.
1.2.6 Electro and control system

The plant will be connected to the local public energy
distribution network system. An emergency electricity supply using a
diesel powered generator (400 V) is foreseen in case of an electrical
energy loss. It is used to provide electrical energy for a save operation
of consumers being important for process-technical reasons and to
important plant equipment (e.g. emergency lightning, fire-fighting pumps)
and the security equipment (e.g. rescue equipment in the waste pit).
The incinerator lines and the equipment for energy
utilisation can be automated to a large extend. The whole plant can be
controlled and supervised from a central control room during normal,
continuous operation.
1.3 Buildings and construction

The description applies to the following objects:
solid waste incineration plant (SWIP) including the
off-loading place, waste pit, boiler house, flue gas cleaning plant,
energy production- and social-/administration buildings.
weigh bridge and infrastructure
The foundation and the wall from the waste pit are of
concrete construction. The other buildings are mainly of steel
construction.
2. 0 ENVIRONMENTAL IMPACT 
The legal local regulations as well as the requirements
for the environmental and personal protection, which have to be met by a
thermal waste treatment plant, will be fully respected.
2.1 Prevention of air pollution

The actual emission of the most important air
pollutants during normal operation are expected to achieve the
concentration limits given by the German regulations (17. BImSchV):
Air pollutant:
|
Unit |
17. BImSchV |
carbon monoxide (CO)
|
mg / Nm3 |
50 1) |
total dust
|
mg / Nm3 |
10 1) |
gaseous. organ. comp. (Ctot.)
|
mg / Nm3 |
10 1) |
gaseous inorg. Cl-comp. (HCl)
|
mg / Nm3 |
10 1) |
gaseous inorg. F-comp. (HF)
|
mg / Nm3 |
1 1) |
sulphur dioxide (SO2)
|
mg / Nm3 |
50 1) |
nitrogen oxides (NOx)
|
mg / Nm3 |
200 1) |
- cadmium (Cd), thallium (Tl),
|
mg / Nm3 |
0,05 2) |
- mercury (Hg)
|
mg / Nm3 |
0,05 2) |
- other metals
|
mg / Nm3 |
0,5 2) |
- dioxins & furanes
|
ng / Nm3 (ITE) |
0,1 2) |
1) average per day
2) average per sampling period
2.2 Odour 
In order to avoid odour emissions from the plant to the
environment, the air from the waste off-loading place and the waste pit
will be evacuated and used as primary combustion air. A complete
destruction of all odour components takes place during the combustion of
the gases.
2.3 Noise 
The legal local requirements concerning noise emissions
from the plant will be met using different noise reducing measures.
Besides, the noise level in zones or rooms within the
plant which require, or are foreseen, for permanent presence of personnel
shall comply with the legal regulations.
2.4 Residues 
Three different kinds of residues are obtained. The
slag can be reused for mainly road construction after minimal treatment.
The boiler ash as well as the residues from semi-dry process should be
brought, due to their content of hazardous metals, to a special landfill.
The boiler ash could be washed and used after drying together with the
slag. The extracted water containing the hazardous metals will be applied
in the semi-dry reactor. So these metals will be chemically fixed with
lime and carried out with the residues from the semi-dry reactor.
. |